The building development at Camberwell College of Arts currently has two strands. One strand is within the new academic building, fit out has begun key areas such as the new library.  The other strand of the works continues at the front of the 1970’s building, behind the hoardings

Last week scaffolding at the back of the Victorian block removed and  a different set of scaffolding was installed at the front of the 1970’s building. The scaffolding at the front (which can be seen when within our current buildings) is to allow contractors safe access. The front windows of the 1970’s building have now been surveyed; this is in preparation for their renovation planned for the summer.