This week at Camberwell College of Arts the development is focused around preparations for the new entrance.  The contractors will be installing scaffolding behind the new hoardings as the first phase of the works will be the removal of the old steps at the front of the 1970’s block.

Alongside our fit out contractors Overbury, BOF have been appointed to provide furniture for the development and we hope to be able to share their mood boards and designs for the furniture shortly. Meanwhile the usual maintenance to existing buildings at Peckham Road continues; for example work has been down to the Bell tower and to the roof of the North block of the Victorian building.