Surveys are being carried out this week at Camberwell’s Peckham Road site, as our fit contractors Overbury begin work. The demolition of the stairs at the front of the 1970’s block will also commence this week; temporary fencing has already been installed in preparation for the works.  It is expected to be a little noisy so we apologise in advance for any inconvenience caused.   

Overbury have set up their site office within the new academic building and the new halls Gardens House has been formally handed over to our accommodation services. This means we should be able to do site tours of both of the new buildings after the Easter break. Meanwhile further work was done to the stained glass window within the Victorian building last week alongside the usual spring maintenance.

 

 

 