Archive for June, 2016

Light well preview: new academic building

Our developers, Hollybrook, are now working on top floor plate of the academic building and we’re into the next round of design fit out meetings for the new academic building with the architects.  One of the features of the new academic building … Continue reading

Progress update and degree shows at Camberwell

Final year undergraduate students and MA Conservation students degree shows opened this weekend at Camberwell College of Arts at both our Peckham Road and Wilson Road sites. There is a brilliant range of thoughtful and beautiful work from students, as showcased on … Continue reading

Inside Look: new accommodation at Camberwell

As covered here last week and on our main website we held a ‘topping out’ ceremony with our developers. The ceremony celebrated that both the new accommodation building and the new academic building at Camberwell College of Arts have now reached full height. We’re … Continue reading

‘Topping Out’ event celebrates key moment in Camberwell development

Camberwell College of Arts celebrated a milestone in the building development works this week, with a ‘topping out’ ceremony which marked the reaching of the highest point in the construction of the two new college buildings. The ceremony was held … Continue reading

Progress Update 6 June 2016

The building development at Camberwell College of Arts on Peckham Road continues to progress well; the final floor of the new academic building is currently being worked on. The current phase is planned to finish mid June and the accommodation building … Continue reading